Latest Updates

We want to keep you informed about the work we're doing. That includes written updates, photos and video, including specific drone footage that gives you the best birds eye view of what's happening. Check below to see what's new and if you have a question, please get in touch with the team.

Latest News

See all news
Piling in action

Progress on piling and temporary terminal works

October 8, 2026

Making an impact You may have heard sounds resounding from the Wellington Ferry Infrastructure project.

Read more

Piling Photo 3

First pile casing pitched – another milestone for the Wellington Ferry Project

September 15, 2026

CentrePort reached a significant milestone for the Ferry Infrastructure Project last week, with the first permanent pile casing being lowered into position.

Read more

Interisland Wharf July 23 2026 Webl Res 21

First set of Temporary Piles at Dock Wharf installed

August 11, 2026

We’ve reached a small milestone for the Ferry Project - The first set of temporary piles have now been installed at Dock Wharf, for the…

Read more

See all news

Update 15 September 2026

The Ferry Infrastructure Project celebrated a significant milestone at CentrePort last week, when the first permanent 24m-long pile was lowered into place by crawler crane.

This marks the start of permanent works to enable the extension of Dock Wharf, which is required for the Cook Strait Interislander Ferry Replacement Programme.

18 permanent piles, 1.8m in diameter, are required for the Dock Wharf extension, and more than 50 permanent piles will be installed across the wider project, alongside the piles already in place to support our staging wharves.

Update 24 August 2026

Our work to install a temporary staging wharf parallel to Dock Wharf is progressing well with 28 piles now in place for this structure. The staging wharf is an important piece of our project as it will be used to enable construction of Dock Wharf's extension. In particular, crawler cranes will sit on the wharf so they have access to where the permanent piles will be installed. 

Permanent piling is scheduled to start in mid-to-late September at the end of Dock Wharf with 1.8m wide steel casings to be driven into the seabed. The casings will eventually be filled with concrete after being prepared and a reinforcing cage being lowered into the empty casing.

Eighteen piles are needed for the Dock Wharf extension structure. Other piles are needed for a further side nesting structure, which will be done using a barge with a crawler crane on top.

You may have seen the steel pile casings neatly stacked for and stored at Kaiwharawhara Point, having been ordered earlier from overseas. This ensured they would be available when we were ready to start piling work, although more are required.

When piling work begins at Dock Wharf, another piling crew will start working on the permanent piling for the Side Nesting Structure. This work will all be done with a crawler crane on a barge. These piles are also 1.8m wide in diameter, like those for Dock Wharf.

Elsewhere on the project, we've been installing new utilities for a temporary terminal building and continuing to remove the old linkspan structure. Both pieces of work should be completed next month.

Update 30 July 2026

Things are gaining momentum at the Kaiwharawhara site with piling for a staging wharf well and truly underway. Some people may have noticed the piling sound and for anyone who's reached out to us, we're keeping an eye (or should that be ear) to the issue with our Acoustic Consultants checking on sound levels.

The team is also starting to have more engagement with the community and key stakeholders to raise awareness about the ferry infrastructure work that CentrePort will deliver. The most recent was a meeting with the Wellington Residents Association Network this week, giving them a presentation on the project. You can access a copy of the presentation given to the group from our Key Documents page.

Consent applications we've submitted to council are beginning to come through, including ones required to set up a temporary terminal for the Interislander. The temporary terminal is needed for safety purposes and to ensure the ongoing operational efficiency of the ferry marine infrastructure works. We'll keep you informed of the details regarding the temporary terminal as it progresses.

Key Documents

Update - July 2026

This 3D video highlights the key upcoming works happening at Kaiwharawhara and the expected final infrastructure designs. 

Update - June 2026

Work is gaining more momentum with materials arriving and set to be stored at the staging wharf area at what CentrePort calls 'South Road'.

These materials have long lead times between order and arrival, so while we're not ready to use some of it, we'd rather have it here for when we need it most! 

These are the casings for the major piles for our wharf extension and they're not your typical house piles. These are up to 2m in diameter - basically the height of basketballer Steven Adams.

We also see the start of piling work for another staging wharf at the Interislander site. This is something that people may hear. Noise will be monitored and generally only happen during the day.

View our prior media releases:

Announcement on Ferries

Ferry Programme Investment

Latest photos

Interislander Upgrade High Res   April 2026 16

Interislander aerial view - April 2026

Interislander Upgrade High Res   April 2026 4

Old piles yet to be removed - April 2026

Interislander Upgrade High Res   April 2026 11

Interislander wharf - April 2026

Interislander Upgrade High Res   April 2026 12

Interislander aerial - April 2026

Interisland Wharf   June 2026 Web Res 17

Interisland Wharf demolition of old structures - June 2026

Interisland Wharf   June 2026 Web Res 6

Interisland Wharf aerial - June 2026

South Gate   June 2026 Web Res 19

South Road removed piles - June 2026

South Gate   June 2026 Web Res 15

South Road staging wharf - June 2026

Southgate 26th July 2026   Web Res 4

Southgate Staging area 26 July

Southgate 26th July 2026   Web Res 18

Southgate aerial 26 July

Interisland Wharf July 23 2026 Webl Res 6

Interisland Wharf 23 July 2026

Interisland Wharf July 23 2026 Webl Res 17

Interisland Wharf barge 23 July 2026

Kaiwharawhara July 23 2026 Web Res 19

Kaiwharawhara Point - piles stacked ready for use 23 July 2026